Works for January 2010

- Pathways will start being pegged out on the 12th January 2010

- Dieback treatment will commence on the 13th January 2010 and take a week to complete (this invloves injecting the trees with a solution to control/combat dieback)

- Digging for the new concrete pathways to commence on the 18th January 2010

STAY TUNED FOR THE NEW PLAYGROUND DESIGN
(Currently in the Design Planning and Equipment placement phase)